Burke, LLC Design/Build was hired by the Conway Park Owners Association to plan, permit, design, and construct a temporary ramp that connects Field Drive to the Lake Forest Tollway Oasis parking lot, providing an alternate route during the reconstruction of Townline Road.  Services were based on a Guaranteed Maximum Price (GMP) for mass earth excavation, asphalt paving, lighting system, I-Pass infrastructure, storm sewer, and erosion control measures.  The Design/Build delivery method enabled us to commence construction prior to design completion, allowing the entire project to be designed, permitted, and built in less than 2 months.

The Details

Location

Lake Forest, Illinois

Construction Cost/Fee

$1.69 million

Client

Conway Park Owners Association