The bridge reconstruction project included removal of the existing seven-span bridge with five continuous steel spans and two simply supported concrete T beams and replacement with galvanized composite steel beams and a continuously reinforced bridge deck. The project also included full replacement of two pier caps and partial replacement of four others, new approach slabs, milling and resurfacing of the adjacent roadways, traffic signal modernization, and deck and underpass lighting.

The Details

Location

Chicago, Illinois

Construction Cost/Fee

$6.4 million / $378 thousand

Client

City of Chicago Department of Transportation